Planning - Subdivision / Resubdivision Application Fees
(adopted: 11/16/2006, effective: 12/7/2006)
  • Copy of subdivision regulations - $10
  • Subdivision/Resubdivision Application Fee Schedule (* Minimum fee if public hearing is required: $800):
    • 1-10 lots $200 per lot*
    • 11-20 lots $250 per lot
    • 21 lots or greater $300 per lot
  • A $60 State fee is added to each application per Connecticut General Statutes Section 22a-27.
  • The Planning Commission reserves the right to apply project review fees such as professional, legal, engineering, et cetera, in addition to administrative fees. These expenses shall be assessed by the Planning Commission and paid by the applicant on an actual and reasonable cost basis after the services are rendered to the Commission.
  • Engineering Fees for Ledyard Subdivisions:
    • Cul-de-sac Fee (permanent OR temporary) $2,500
    • Detention Basin $500
    • Each structure (e.g.: catch basin, man hole cover) $25
    • Modification of Approval Fee $500
    • New Road or extension of existing road: $5 per linear foot*
*The linear foot fee shall be calculate by measuring along the distance of the road center line from the point of beginning of the new intersection to the end point of the next intersection or, if a cul-de-sac, to the center of the cul-de-sac bulb.

Forms Available On-line (Click On Form Name to Access Form)
(Note: Forms can now be filled in on-line and printed; completed forms and fees must still be brought to the Town Hall for processing.)